Akhir Desember Fly Over Permata Hijau Rampung
.
photo Izzudin - Beritajakarta.id

Permata Hijau Flyover Construction to Finish This December

Jakarta Bina Marga Department predicted Permata Hijau, Kebayoran Lama Flyover construction will be complete by the end of year. The current construction has reached 87 percent and cost Rp 131 billion.

The contruction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent

 

“The construction progress has reached 87 percent from the initial plan 71.12 percent by deviation occurs 15.37 percent,” said Hananto, Section Head of overpass and intersection division for Jakarta Bina Marga Department, Thursday (10/22).

Illegal Parking Under Roxy Flyover Rampant

 

According to him, the construction of 623 meters long flyover now is remaining box girder project above railway and finishing touch.

 

The flyover width is about 10 meters and there will be two lanes by each width is 7.8 meters. The remaining area will be used for pedestrian track.

 

“There will be two lanes towards Permata Hijau and Patal Senayan,” he disclosed.

Linked News
Popular News indeks
  1. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye381 personNurito
  2. Rano Supports Schools to Organize Study Tours to Museums

    access_time08-03-2025 remove_red_eye300 personBudhi Firmansyah Surapati
  3. TMII Launches Jelajah Cerita Ramadan Program with Umroh Grand Prize

    access_time08-03-2025 remove_red_eye296 personNurito
  4. North Jakarta PPKD Provides Training for Students with Disabilities

    access_time07-03-2025 remove_red_eye294 personAnita Karyati
  5. BPPOM Finds Harmful Substances in Ramadhan Takjil Snacks in Rawamangun Market

    access_time07-03-2025 remove_red_eye292 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik